Laying of 69 kv power cable.
- Version
- Download 4
- File size 1.25 MB
- File count 1
- Creation date n 18 September, 2022
- Last updated 18 September, 2022
Laying of 69 kv power cable.
Procedure: once the trench has been excavated; and if it is the case with the respective bed of classified soil; the cable is lowered into the trench; Laying is done with a 583 Side Boom or PC220LC-8 Backhoe Loader; which lifts the reel and moves moving it and uncoiling it with personnel with sufficient experience for this purpose who will control the progress of the laying; the cable must fall due to gravity; while qualified personnel (2) will comb the cable properly, checking that they do not overlap; The combing will be carried out by qualified personnel for this purpose (electrical minimum b) who will strap every 5 meters.